Home NATIONAL NEWS TRABAHO NG SENADO DAPAT MAGPATULOY SA KABILA NG INGAY SA PULITIKA — GATCHALIAN

Unang phase ng EDSA rehabilitation, magsisimula na mamayang gabi

by DWIZ 882 December 24, 2025 0 comment
EDSA

Magsisimula na mamayang gabi ang rehabilitasyon ng EDSA, na ayon sa Department of Public Works and Highways, ay magtatapos sa Enero 4, 2026.

Nabatid na inilabas ng DPWH—NCR ang schedule nito mula Disyembre 24o hanggang 27, kung saan ilang bahagi ng EDSA ang isasara upang ayusin ang mga sirang bahagi at lagyan ng aspalto ang kahabaan ng nasabing highway, na “round-the-clock” gagawin ng kawani ng kagawaran.

Ang mga sumusunod na bahagi ng EDSA ay isasara para sa concrete reblocking:

Southbound

December 24–27, 2025: P. Celle Street to Roxas Boulevard (inner lane only)

December 26–27, 2025: Tramo Flyover to P. Celle Street (inner lane only)

Northbound

December 24–27, 2025: Roxas Boulevard to Park Avenue (inner lane only)

December 27, 2025: Park Avenue to Taft Avenue (inner lane)

Samantala, lalapatan naman ng aspalto ang mga sumusunod na bahagi ng EDSA:

December 25, 2025: EDSA Orense to Urdaneta Village

December 26, 2025: EDSA Orense to Magallanes Interchange

December 27, 2025: Tramo to Loring Street (inner lane to outer lane)

Inaasahan namang ilalabas ng kagawaran ang updated rehabilitation schedule mula Disyembre 28o hanggang Enero 5, 2026.

Comments

comments

You may also like

Leave a Comment